Buena Vista Park Court Reconstruction
Project B#: 40-B223506
Overall Project Cost: $675,000 (Design and Construction)



The elements of the project include:
- Demolish and reconstruct three basketball courts
- Incorporate a pickleball court onto one court
- Construction swales per DERM drainage requirements
- Landscape with ground covering
Funding Sources: Impact Fees New Ordinance 2007 Park
Project Start Date: February 19, 2025
Project Completion: November 19, 2025