NW 6 Street Roadway & Drainage Improvements
Project No.: 40-B173645
Location: NW 6 Street from NW 11 Avenue to NW 12 Avenue
This project is located in District 3
Notice of Construction Work
The City of Miami will be making much needed roadway improvements and repairs during the next few months. Personnel and equipment from H&J Asphalt Inc., will be working in your neighborhood during this time.
Scope of Work:
Road repair and drainage improvements, including but not limited to grading, milling and resurfacing, local drainage improvements, curb and gutter, and concrete sidewalks
Construction Timeframe:
Construction for this project is anticipated to commence in July 2019, and it is anticipated to be completed by October 2019. Please note that this schedule may change due to adverse weather or other unexpected conditions.
Total Project Cost:
$75,679
Contractor:
H&J Asphalt Inc.
Hours of Operation:
8:00am to 5:00pm
Monday through Friday
Lane Closure:
Lane closures may occur but accessibility to local traffic and pedestrians will be maintained at all times.