NW 17 St from NW 14 Ave to NW 15 Ave Roadway & Drainage Improvements
Project Number: 40-B30262
Current Project Status:
Construction.
Project Scope:
The new construction work consists of new asphalt, new drainage, new ADA ramps, and new valley gutter.
Project Cost Estimate:
$293,520
Project Boundaries:
The project limits are bound by NW 17th St from NW 14th Ave to NW 15th Ave.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
(Subject to change based on project conditions)
- Planned Construction Start: February 2026.
- Planned Construction End: April 2026.
Disclaimer: The timeline provided is an estimate and may be adjusted due to factors such as weather conditions, or other unforeseen circumstances.