NW 17 Street Roadway Improvements
Two Roadway Improvements in the Grapeland Neighborhood on NW 17 Street in City of Miami, District 1

Project Number: 40-B183611A (Phase I) / 40-B183611 (Phase II)
Current Project Status (January 2026):
40-B183611A Construction Procurement.
40-B183611 Design.
Project Scope:
Design and construction of roadway and stormwater infrastructure improvements including roadway reconstruction, curbs, sidewalks, swale regrading / sodding, driveways approaches, ADA ramps, on-street parking, drainage system, and signage and pavement markings. This project also includes a Joint Participation Agreement (JPA) with Miami-Dade Water and Sewer (MDWASD) for the installation of an 8-inch water main, fire hydrants, and water services.
Project Phases:
Phase I (40-B183611A) - From NW 32 to NW 37 Avenue.
Phase II (40-B183611) - From NW 27 to NW 32 Avenue.
Project Cost Estimate:
40-B183611A: $7,473,497
40-B183611: $7,856,143
Project Benefits and Impacts:
- Number of properties impacted: Total = 139 (106 Residential and 33 Non-Residential)
- Total property value protected: $82M
Project Boundaries:
- 40-B183611A - NW 17 Street between NW 32 Avenue and NW 37 Avenue
- 40-B183611 - NW 17 Street between NW 27 Avenue and NW 32 Avenue

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Construction Schedule:
The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.
- Construction Start:
40-B183611A - June 2026
40-B183611 - January 2028
- Construction End:
40-B183611A - June 2027
40-B183611 - January 2029