NW 17 Street Roadway Improvements

Two Roadway Improvements in the Grapeland Neighborhood on NW 17 Street in City of Miami, District 1

Miami Forever Bond Logo U.S. Department of Housing and Urban Development Logo Citizen's Independent Transportation Trust Logo

Project Number: 40-B183611A (Phase I) / 40-B183611 (Phase II)

Current Project Status:

40-B183611A Bidding Phase, 100% plans approved in May 2025.

40-B183611 Design Phase, Typical Section Package.

Project Scope:

Design and construction of roadway and stormwater infrastructure improvements including roadway reconstruction, curbs, sidewalks, swale regrading / sodding, driveways approaches, ADA ramps, on-street parking, drainage system, and signage and pavement markings. This project also includes a Joint Participation Agreement (JPA) with Miami-Dade Water and Sewer (MDWASD) for the installation of an 8-inch water main, fire hydrants, and water services.

Project Phases:

Phase I (40-B183611A): From NW 32 to NW 37 Avenue.

Phase II (40-B183611): From NW 27 to NW 32 Avenue.

Project Cost Estimate:

40-B183611A: $7,473,497

40-B183611: $7,696,320

Project Benefits and Impacts:

  • Number of properties impacted: Total = 139 (106 Residential and 33 Non-Residential)
  • Total property value protected: $82M

Project Boundaries:

  • 40-B183611A - NW 17 Street between NW 32 Avenue and NW 37 Avenue
  • 40-B183611 - NW 17 Street between NW 27 Avenue and NW 32 Avenue

 Map indicating 40-B183611A and 40-B183611 Project Boundaries

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Estimated Construction Timeline:

Subject to change.

  • Estimated Construction Start:
    Phase 1 - Summer 2026
    Phase 2 - Winter 2027
  • Estimated Construction End:
    Phase 1 - Summer 2027
    Phase 2 - Winter 2028

Provide your feedback about this project here