NW 17 Street Roadway Improvements

Miami Forever Bond Logo U.S. Department of Housing and Urban Development Logo Citizens' Independent Transportation Trust Logo

Project Number: 40-B183611A (Phase I) / 40-B183611 (Phase II)

Current Project Status (May 2026):

40-B183611A Pre-Construction.

40-B183611 Design.

Project Scope:

Design and construction of roadway and stormwater infrastructure improvements including roadway reconstruction, curbs, sidewalks, swale regrading / sodding, driveways approaches, ADA ramps, on-street parking, drainage system, and signage and pavement markings. This project also includes a Joint Participation Agreement (JPA) with Miami-Dade Water and Sewer (MDWASD) for the installation of an 8-inch water main, fire hydrants, and water services.

Project Phases:

Phase I (40-B183611A) - From NW 32 to NW 37 Avenue.

Phase II (40-B183611) - From NW 27 to NW 32 Avenue.

Estimated Costs:

40-B183611A: $7,473,497
40-B183611: $7,856,143

Project Boundaries:

  • 40-B183611A: NW 17 Street between NW 32 Avenue and NW 37 Avenue.
  • 40-B183611: NW 17 Street between NW 27 Avenue and NW 32 Avenue.

 Map illustrating the project boundaries of 40-B183611A and 40-B183611

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start Date:
    40-B183611A - June 2026
    40-B183611 - March 2028
  • Construction End Date:
    40-B183611A - June 2027
    40-B183611 - March 2029