Shoreline Repair Mini Rapids Park
Project Number: 40-B253603
Current Project Status (September 2025):
A/E Selection.
Project Scope:
Design and construction of improvements to stabilize short segments of the shoreline along the Miami River which will be treated as emergency type repairs.
Project Cost Estimate:
$1,338,375
Project Boundaries:
The project limits are bounded by
First location is approximately 200ft along the NW S River Drive embankment on the south side of the Miami River in front of the Miami River Rapids Mini Park.
Second location is approximately 60ft along the NW N River Drive embankment on the north side of the Miami River where NW N River Drive intersects with NW 25 Ave.


Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
- Estimated Construction Start: Winter 2027
- Estimated Construction End: Fall 2027