Morningside NE 50 Ter and NE 5 Ave Drainage and Roadway Improvements
Project Number: 40-B263603
Current Project Status:
Construction.
Project Scope:
The new construction work consists of new asphalt, new drainage, new sidewalk, new driveway approaches, swale restoration, new ADA ramps and new curb and gutter.
Estimated Costs:
$989,906
Project Boundaries:
The project limits are bound by NE 50th Terrace from east of Biscayne Blvd to NE 7th Avenue and NE 5th Avenue from NE 50th Terrace to NE 55th Terrace.
Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Construction Schedule:
The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.
- Construction Start Date: July 2026
- Construction End Date: November 2026