Tigertail Ave Traffic Calming

Project Number: 40-B253606
Current Project Status (June 2025):
- Location A: A/E Selection
- Location B: Construction
- Location C: Design
Project Scope:
Assessment of locations for traffic calming device installations; balloting of applicable locations; design and construction of traffic calming devices at eligible locations.
Project Cost Estimate:
$1,192,125
Project Benefits and Impacts:
- Number of properties impacted: Total = 8 (7 Residential and 1 Non-Residential)
- Total property value protected: $32M
Project Boundaries:
The project limits are bounded by Tigertail Ave & Kirk Ave: Raised Intersection; Tigertail Ave between Jefferson St & Washington St: Speed Cushions; Tigertail Ave & Aviation: Intersection Improvements on the northeast corner.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
Subject to change.
- Estimated Construction Start: Summer 2025
- Estimated Construction End: January 2027
Provide your feedback about this project here