Tigertail Ave Traffic Calming

Citizens' Independent Transportation Trust Logo

Project Number: 40-B253606

Current Project Status (June 2026):

  • Location A: Design (Construction Start Date: November 2026 and Construction End Date: June 2027)
  • Location B: Construction Completed!
  • Location C: Design

Project Scope:

Assessment of three locations for traffic calming device installations; balloting of applicable locations; design and construction of traffic calming devices at eligible locations.

Estimated Costs:

$1,092,788

Project Boundaries:

The project limits are bounded by

  • Location A (Tigertail Ave & Kirk St): Raised Intersection.
  • Location B (Tigertail Ave between Jefferson St & Washington St): Speed Cushions.
  • Location C (Tigertail Ave & Aviation Ave): Intersection Improvements.

Map illustrating the project boundaries of 40-B253606

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start Date: Winter 2025
  • Construction End Date: July 2027