Tigertail Ave Traffic Calming

Project Number: 40-B253606
Current Project Status (June 2026):
- Location A: Design (Construction Start Date: November 2026 and Construction End Date: June 2027)
- Location B: Construction Completed!
- Location C: Design
Project Scope:
Assessment of three locations for traffic calming device installations; balloting of applicable locations; design and construction of traffic calming devices at eligible locations.
Estimated Costs:
$1,092,788
Project Boundaries:
The project limits are bounded by
- Location A (Tigertail Ave & Kirk St): Raised Intersection.
- Location B (Tigertail Ave between Jefferson St & Washington St): Speed Cushions.
- Location C (Tigertail Ave & Aviation Ave): Intersection Improvements.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Construction Schedule:
The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.
- Construction Start Date: Winter 2025
- Construction End Date: July 2027