NW 9 Ave from NW 2 St to NW 3 St Drainage and Roadway Improvements

U.S. Department of Housing and Urban Development Logo

Project Number: 91-04273

Current Project Status:

Construction.

Project Scope:

The new construction work consists of new asphalt, new drainage, new sidewalks, new curb and gutter, new ADA ramps, and new valley gutter.

Estimated Costs:

$600,000

Project Boundaries:

The project limits are bound by NW 9 Ave from NW 2 St to NW 3 St.

Map illustrating the project boundaries of 91-04273

Road Closures:

Please note that some road closures may be necessary during the construction period; however, they will be carefully sequenced to minimize disruption to residents.

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start Date: August 2026
  • Construction End Date: October 2026