SE/SW 25 Road between Brickell Avenue and Northbound On-Ramp to I-95

Project Number: 40-B73102E
Current Project Status (October 2025):
Construction.
Project Scope:
The new construction work consists of milling and resurfacing the existing asphalt pavement and restoring pavement markings.
Project Cost Estimate:
$86,066
Project Boundaries:
The project limits are bound by SE/SW 25 Road between Brickell Avenue and Northbound On-Ramp to I-95.

Road Closures:
Please note that some road closures may be necessary during the construction period; however, they will be carefully sequenced to minimize disruption to residents.
Estimated Construction Timeline:
Subject to change.
- Estimated Construction Start: October 2025
- Estimated Construction End: October 2025
Please note that these dates are tentative and may be adjusted due to unforeseen circumstances such as weather conditions or other operational factors.