SW 21 St from SW 18 Ave to SW 19 Ave Drainage and Roadway Improvements

Project Number: 40-B233819

Current Project Status:

Construction.

Project Scope:

The new construction work consists of drainage improvement, landscaping improvement, new asphalt, new curb and gutter and ADA ramps. 

Project Cost Estimate:

$240,000

Project Boundaries:

The project limits are bound by SW 21st Street from SW 18th Avenue to SW 19th Avenue.

SW 21 St from SW 18 Ave to SW 19 Ave Drainage and Roadway Improvements.jpg

Road Closures:

Please note that some road closures may be necessary during the construction period; however, they will be carefully sequenced to minimize disruption to residents.

Estimated Construction Timeline:

Subject to change.

  • Estimated Construction Start: May 2026
  • Estimated Construction End: June 2026

Please note that these dates are tentative and may be adjusted due to unforeseen circumstances such as weather conditions or other operational factors.