SW 21 Ter from SW 18 Av to SW 19 Av Drainage and Roadway Improvements

Project Number: 40-B233819

Current Project Status:

Construction.

Project Scope:

The new construction work consists of drainage improvement, new curb and gutter, new asphalt, new ADA ramps and swale restoration.

Estimated Costs:

$205,900

Project Boundaries:

The project limits are bound by SW 21st Terrace from SW 18th Avenue to SW 19th Avenue.

Map illustrating the project boundaries of 40-B233819

Road Closures:

Please note that some road closures may be necessary during the construction period; however, they will be carefully sequenced to minimize disruption to residents.

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start Date: October 2026
  • Construction End Date: November 2026