District 4 Traffic Calming Devices Phase II
Project Number: 40-B233607
Project Scope:
Assessment of twenty-six locations for geometric fit for traffic calming device installations; balloting of acceptable locations; design and construction of traffic calming devices at eligible locations.
Project Costs Estimate:
$1,335,790
Project Benefits and Impacts:
- Number of properties impacted: Total = 76 (70 Residential and 6 Non-Residential)
- Total property value protected: $64M
Project Boundaries:
Group 1
#48: SW 10 St between SW 22 Ave and SW 23 Ave
#49: SW 10 St between SW 17 Ave and SW 18 Ave (D3)
#50: SW 10 St between SW 25 Ave and SW 27 Ave
#51: SW 12 St between SW 21 Ave and SW 22 Ave (D3)
#52: SW 17 St between SW 24 Ave and SW 23 Ave
#53: SW 17 St between SW 17 Ave and SW 18 Ave (D3)
#54: SW 17 St between SW 37 Ave and SW 36 Ave
Group 2
#45: SW 6 St between SW 39 Ave and SW 39 Ct
#46: SW 4 St between SW 47 Ave and SW 48 Ave
#56: NW 69 Ave between W Flagler St and Tamiami Canal Rd
#57: SW 69 Ave between SW 1 St and SW 2 St
#58: SW 69 Ave between SW 5 St and SW 5 Ter
#59: SW 63 Ave between W Flagler St and SW 2 St
#61: SW 63 Ave between SW 2 St and SW 4 St
#63: SW 63 Ave between SW 6 St and SW 8 St (C)
Group 3
#43A: Tamiami Boulevard between SW 4 St and SW 6 St
#67: SW 34 Ave between SW 2 St and SW 3 St
#69: SW 34 Ave between SW 6 St and SW 7 St
Group 4
#44A: SW 55 Ave Rd between SW 2 St and SW 57 Ave (I)
#64: NW 34 Ave between NW 4 Ter and NW 4 St (I)
#65: NW 34 Ave between NW 4 St and NW 3 St (I)
#66: NW 34 Ave between NW 2 St and NW 1 St (I)
#70: SW 33 Ct between SW 18 St and SW 20 St (I)
Group 5
#72: NW 6 St between NW 28 Ave and NW 30 Ave (S)
Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
- Estimated Construction Start: Spring 2027
- Estimated Construction End: Winter 2027
Provide your feedback about this project here