District 4 Traffic Calming Devices Phase II

Citizens' Independent Transportation Trust Logo

Project Number: 40-B233607

Current Project Status (November 2025):

Construction. Please see Project Boundaries section to view each Traffic Control Status.

Project Scope:

Assessment of twenty-six locations for geometric fit for traffic calming device installations; balloting of acceptable locations; design and construction of traffic calming devices at eligible locations.

Project Costs Estimate:

$991,469 

Project Boundaries:

Group 1

48: SW 10 St between SW 22 Ave and SW 23 Ave - Built
49: SW 10 St between SW 17 Ave and SW 18 Ave (D3) - Built
50: SW 10 St between SW 25 Ave and SW 27 Ave - Built
51: SW 12 St between SW 21 Ave and SW 22 Ave (D3) - Built
52: SW 17 St between SW 24 Ave and SW 23 Ave - Built
53: SW 17 St between SW 17 Ave and SW 18 Ave (D3) - Built
54: SW 17 St between SW 37 Ave and SW 36 Ave - Built

Group 2

45: SW 6 St between SW 39 Ave and SW 39 Ct - Built
46: SW 4 St between SW 47 Ave and SW 48 Ave - Built
56: NW 69 Ave between W Flagler St and Tamiami Canal Rd - Built
57: SW 69 Ave between SW 1 St and SW 2 St - Built
58: SW 69 Ave between SW 5 St and SW 5 Ter - Built
59: SW 63 Ave between W Flagler St and SW 2 St - Built
61: SW 63 Ave between SW 2 St and SW 4 St - Built
63: SW 63 Ave between SW 6 St and SW 8 St - Built

Group 3

43A: Tamiami Boulevard between SW 4 St and SW 6 St - Under Construction
67: SW 34 Ave between SW 2 St and SW 3 St - Under Construction
69: SW 34 Ave between SW 6 St and SW 7 St - Under Construction

Group 4

44A: SW 55 Ave Rd between SW 2 St and SW 57 Ave - Built
70: SW 33 Ct between SW 18 St and SW 20 St - Built

Group 5

72: NW 6 St between NW 28 Ave and NW 30 Ave - Pending Traffic Study

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start (Group 3): November 2025
  • Construction End (Group 3): Summer 2026