District 4 Traffic Calming Devices Phase II
Project Number: 40-B233607
Current Project Status (June 2025):
Construction.
Project Scope:
Assessment of twenty-six locations for geometric fit for traffic calming device installations; balloting of acceptable locations; design and construction of traffic calming devices at eligible locations.
Project Costs Estimate:
$1,348,267
Project Benefits and Impacts:
- Number of properties impacted: Total = 76 (70 Residential and 6 Non-Residential)
- Total property value protected: $64M
Project Boundaries:
Group 1
48: SW 10 St between SW 22 Ave and SW 23 Ave
49: SW 10 St between SW 17 Ave and SW 18 Ave (D3)
50: SW 10 St between SW 25 Ave and SW 27 Ave
51: SW 12 St between SW 21 Ave and SW 22 Ave (D3)
52: SW 17 St between SW 24 Ave and SW 23 Ave
53: SW 17 St between SW 17 Ave and SW 18 Ave (D3)
54: SW 17 St between SW 37 Ave and SW 36 Ave
Group 2
45: SW 6 St between SW 39 Ave and SW 39 Ct
46: SW 4 St between SW 47 Ave and SW 48 Ave
56: NW 69 Ave between W Flagler St and Tamiami Canal Rd
57: SW 69 Ave between SW 1 St and SW 2 St
58: SW 69 Ave between SW 5 St and SW 5 Ter
59: SW 63 Ave between W Flagler St and SW 2 St
61: SW 63 Ave between SW 2 St and SW 4 St
63: SW 63 Ave between SW 6 St and SW 8 St (C)
Group 3
43A: Tamiami Boulevard between SW 4 St and SW 6 St
67: SW 34 Ave between SW 2 St and SW 3 St
69: SW 34 Ave between SW 6 St and SW 7 St
Group 4
44A: SW 55 Ave Rd between SW 2 St and SW 57 Ave (I)
64: NW 34 Ave between NW 4 Ter and NW 4 St (I)
65: NW 34 Ave between NW 4 St and NW 3 St (I)
66: NW 34 Ave between NW 2 St and NW 1 St (I)
70: SW 33 Ct between SW 18 St and SW 20 St (I)
Group 5
72: NW 6 St between NW 28 Ave and NW 30 Ave (S)
Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
Subject to change.
- Estimated Construction Start: Winter 2026
- Estimated Construction End: Summer 2026
Provide your feedback about this project here