District 4 Traffic Calming Devices Phase II

Project Number: 40-B233607

Project Scope:

Assessment of twenty-six locations for geometric fit for traffic calming device installations; balloting of acceptable locations; design and construction of traffic calming devices at eligible locations.

Project Costs Estimate:

$1,335,790

Project Benefits and Impacts:

  • Number of properties impacted: Total = 76 (70 Residential and 6 Non-Residential)
  • Total property value protected: $64M

Project Boundaries:

Group 1

#48: SW 10 St between SW 22 Ave and SW 23 Ave

#49: SW 10 St between SW 17 Ave and SW 18 Ave (D3)

#50: SW 10 St between SW 25 Ave and SW 27 Ave

#51: SW 12 St between SW 21 Ave and SW 22 Ave (D3)

#52: SW 17 St between SW 24 Ave and SW 23 Ave

#53: SW 17 St between SW 17 Ave and SW 18 Ave (D3)

#54: SW 17 St between SW 37 Ave and SW 36 Ave

 

Group 2

#45: SW 6 St between SW 39 Ave and SW 39 Ct

#46: SW 4 St between SW 47 Ave and SW 48 Ave

#56: NW 69 Ave between W Flagler St and Tamiami Canal Rd

#57: SW 69 Ave between SW 1 St and SW 2 St

#58: SW 69 Ave between SW 5 St and SW 5 Ter

#59: SW 63 Ave between W Flagler St and SW 2 St

#61: SW 63 Ave between SW 2 St and SW 4 St

#63: SW 63 Ave between SW 6 St and SW 8 St (C)

 

Group 3

#43A: Tamiami Boulevard between SW 4 St and SW 6 St

#67: SW 34 Ave between SW 2 St and SW 3 St

#69: SW 34 Ave between SW 6 St and SW 7 St

 

Group 4

#44A: SW 55 Ave Rd between SW 2 St and SW 57 Ave (I)

#64: NW 34 Ave between NW 4 Ter and NW 4 St (I)

#65: NW 34 Ave between NW 4 St and NW 3 St (I)

#66: NW 34 Ave between NW 2 St and NW 1 St (I)

#70: SW 33 Ct between SW 18 St and SW 20 St (I)

 

Group 5

#72: NW 6 St between NW 28 Ave and NW 30 Ave (S)

 

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Estimated Construction Timeline:

  • Estimated Construction Start: Spring 2027
  • Estimated Construction End: Winter 2027