NW 4 ST from NW 30 AV to NW 32 AV Roadway and Drainage Improvements

U.S. Department of Housing and Urban Development Logo

Project Number: 91-04221

Current Project Status (September 2025):

Construction.

Project Scope:

The new construction work consists of new asphalt, new drainage, new ADA ramps, and new valley gutter.

Project Cost Estimate:

$500,162

Project Boundaries:

The project limits are bound by NW 4 St from NW 30 Ave to NW 32 Ave.

Map illustrating the project boundaries of 91-04221

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Estimated Construction Timeline:

Subject to change.

  • Estimated Construction Start: September 2025
  • Estimated Construction End: January 2026