SW 24 Street from SW 27 Avenue to SW 32 Avenue

Miami Forever Bond Logo Citizens' Independent Transportation Trust Logo Florida Department of Environmental Protection Logo

This work was funded in part through a grant agreement from the Florida Department of Environmental Protection's Office of Resilience and Coastal Protection Resilient Florida Program. The views, statements, findings, conclusions, and recommendations expressed herein are those of the author(s) and do not necessarily reflect the views of the State of Florida or any of its subagencies.
February 2025.

Project Number: 40-B50413

Current Project Status (January 2026):

Construction Completed! 

Project Scope:

Design and construction of right-of-way improvements including driveway approaches, sidewalks, ADA ramps, valley gutters, curbs, drainage system, milling and resurfacing, roadway reconstruction, pavement markings and signage, swale regrading and sodding, and landscaping. This project also includes a Joint Participation Agreement (JPA) with the Miami-Dade Water and Sewer Department (MDWASD) for the installation of an 8-inch watermain, water service connections, and fire hydrants.

Project Cost Estimate:

$8,478,403 

Project Boundaries:

The project limits are bounded by

Original: SW 24 Street between SW 27 Avenue and SW 32 Avenue.
Side Streets: SW 31 Avenue between SW 24 Street and SW 25 Street; SW 29 Avenue between SW 24 Terrace and SW 25 Street.

Map illustrating the project boundaries of 40-B50413

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start: Summer 2024
  • Construction End: Winter 2025