SW 5 Street from SW 29 Avenue to SW 32 Avenue Reconstruction

Project Number: 40-B203610
Current Project Status (November 2025):
Construction Completed!
Project Scope:
Design and construction of right-of-way improvements including roadway reconstruction, drainage system, curbs and gutters, valley gutters, ADA ramps, and tree removals and new tree planting.
Project Cost Estimate:
$2,584,378
Project Boundaries:
The project limits are bounded by SW 5 Street between SW 29 Avenue and SW 32 Avenue.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Construction Schedule:
The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.
- Construction Start: Spring 2025
- Construction End: Fall 2025