Buena Vista Local Drainage and Road Improvements

Miami Forever Bond Logo

Project Number: 40-B233602

Current Project Status (June 2025):

Design. 90% plans by early June 2025.

Project Scope:

Design and construction of right-of-way improvements including drainage system, partial roadway reconstruction, milling and resurfacing, sidewalks, curbs and gutters, landscaping, and lighting.

Project Cost Estimate:

$5,497,511

Project Benefits and Impacts:

The project will help alleviate localized flooding experienced by the community.

  • Number of properties impacted: Total = 87 (56 Residential and 31 Non-residential)
  • Total property value protected: $77M

Project Boundaries:

The project limits are bounded by NE 49 Street and NE 50 Street between North Miami Avenue and NE 2 Avenue.

Map indicating 40-B233602 Project Boundaries

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Estimated Construction Timeline:

Subject to change.

  • Estimated Construction Start: Winter 2026
  • Estimated Construction End: Winter 2027

Provide your feedback about this project here