Project Number: 40-B243610

Current Project Status (November 2025):

Group 1: Construction.

Group 2: Design.

Group 3: Construction completed!

Project Scope:

Assessment of twelve (12) locations for traffic calming measures, balloting of applicable locations; design and construction of traffic calming devices at eligible locations.

Project Cost Estimate:

$1,991,985 

Project Boundaries:

The project limits are bounded by 

Phase I

Group 1

1: NW 6 Ave between NW 44 St and NW 45 St (speed hump)
2: NW 6 Ave between NW 42 St and NW 43 St (speed hump)
3: NW 40 St between NW 5 Ave and NW 6 Ave (speed hump)

Group 2

7: NW 69 St and NW 2 Ct (textured pavement)
9: NW 69 St and NW 4 Ave (textured pavement)
13: NW 69 St and NW 2 Ct (textured pavement)

Group 3

10: NW 50 St between NW 12 Ave and NW 13 Ave (raised crosswalk)
11: NW 50 St and NW 13 Ave (west n/s crosswalk)
12: NW 50 St between NW 13 Ave and NW 14 Ave (speed table)

Group 4

4: NE 82 Ter and NE 1 Pl (textured pavement)
5: NE 1 Pl between NE 82 St and NE 82 Ter (speed hump)
14: Federal Highway between NE 36 St and NE 54 St (scope not yet defined)

Map illustrating the project boundaries of 40-B243610

Map illustrating the project boundaries of 40-B243610

Map illustrating the project boundaries of 40-B243610

Map illustrating the project boundaries of 40-B243610

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

Group 1:

  • Construction Start: October 2025
  • Construction End: January 2026

Group 2:

  • Construction Start: October 2026
  • Construction End: March 2027