District 5 Traffic Calming

Project Number: 40-B243610
Project Scope:
Design and construction of traffic calming measures at six eligible locations.
Project Cost Estimate:
$1,000,000
Project Benefits and Impacts:
- Number of properties impacted: Total = 543 (380 Residential and 163 Non-Residential)
- Total property value protected: $731M
Project Boundaries:
- Federal Highway between NE 36 St to NE 54 St
- NE 1 Pl between NE 82 St and NE 82 Ter
- NE 82 Ter at NE 1 Pl: Stop bar at NE 1 Pl; Speed Hump along NE 1 Pl between NE 82 Ter and NE 82 St.
- NW 41 St at NW 10 Ave: All-Way Stop Control (Work to be performed by MDC-DTPW)
- NW 50 St between NW 12 Ave and NW 15 Ave
- NW 69 St between NW 2 Ave and NW 5 Ave


Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
- Estimated Construction Start: Winter 2026
- Estimated Construction End: Summer 2027
Provide your feedback about this project here