NE 3 Avenue from NE 54 Street to NE 59 Street
Project Number: 40-B50906
Project Scope:
Design and construction of roadway and drainage improvements including roadway reconstruction, swale reconstruction, sidewalk repairs, ADA ramps, drainage system, and striping.
Project Cost Estimate:
$3,259,046
Project Benefits and Impacts:
- Number of properties impacted: Total = 32 (14 Residential and 18 Non-Residential)
- Total property value protected: $14M
Project Boundaries:
The project limits are bounded by NE 3 Avenue from NE 54 Street to NE 59 Street.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
- Estimated Construction Start: Fall 2025
- Estimated Construction End: Winter 2026
Provide your feedback about this project here