NW 5th Avenue Traffic Calming Devices

Citizen's Independent Transportation Trust

Project Number: 40-B233603

Current Project Status (June 2025):

Construction.

Project Scope:

Design and construction of traffic calming devices (one raised intersection, one speed hump, and bulb-outs) and milling and resurfacing.

Project Cost Estimate:

$1,410,093

Project Benefits and Impacts:

  • Number of properties impacted: Total = 59 (47 Residential and 12 Non-Residential)
  • Total property value protected: $30M

Project Boundaries:

The project limits are bounded by NW 5 Avenue between NW 42 Street and NW 51 Street. See proposed traffic calming locations in the graphic below.

NW 5 Avenue between NW 42 Street and NW 43 Street (Speed Hump).
NW 5 Avenue at NW 48 Street (Bulb-out).
NW 5 Avenue at NW 50 Street (Raised Intersection).
NW 5 Avenue at NW 51 Street (Bulb-out).

5th Avenue Traffic Calming Devices Map 2025

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Estimated Construction Timeline:

Subject to change.

  • Notice to Proceed has been provided to the contractor: March 2025
  • Contractor has obtained permits. Completion of permitting process: April 2025
  • Start of construction: May 2025
  • Estimated Construction End: Spring 2026