NW 5th Avenue Traffic Calming Devices

Citizens' Independent Transportation Trust Logo

Project Number: 40-B233603

Current Project Status (May 2026):

Construction completed!

May 2026 Construction Completion Photos

NW 5th Avenue Traffic Calming Devices Completed

NW 5th Avenue Traffic Calming Devices Completed

March 2026 Construction Progress Photos

NW 5th Avenue Traffic Calming Devices Progress

NW 5th Avenue Traffic Calming Devices Progress

NW 5th Avenue Traffic Calming Devices Progress

Project Scope:

Design and construction of traffic calming devices (one raised intersection, one speed hump, and bulb-outs) and milling and resurfacing.

Project Cost Estimate:

$1,296,255 

Project Boundaries:

The project limits are bounded by NW 5 Avenue between NW 42 Street and NW 51 Street. See proposed traffic calming locations in the graphic below.

NW 5 Avenue between NW 42 Street and NW 43 Street (Speed Hump).
NW 5 Avenue at NW 48 Street (Bulb-out).
NW 5 Avenue at NW 50 Street (Raised Intersection).
NW 5 Avenue at NW 51 Street (Bulb-out).

Map illustrating the project boundaries of 40-B233603

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Construction Schedule: 

  • Notice to Proceed has been provided to the contractor: March 2025
  • Contractor has obtained permits. Completion of permitting process: April 2025
  • Start of construction: May 2025
  • Construction End: Spring 2026