Bayhomes Drive Drainage Improvements
Project Number: 40-B30846
Project Scope:
The project has two phases. Phase 1A - Design and construction of right of way improvements including roadway reconstruction, milling and resurfacing, drainage, minor driveway and sidewalk work and installation of one new injection well, Phase 1B - Deep cleaning of the existing wells. Assessment of site. Design and construction of new drainage, including new injection wells, as applicable.
Project Estimate:
$1,050,000
Project Benefits and Impacts:
The project will help alleviate localized flooding experienced by the community.
- Number of properties impacted: Total = 35 Total (35 Residential)
- Total property value protected: $60M
Project Boundaries:
The project limits are bounded by North Bay Homes Drive between SW 37 Avenue and South Bay Homes Drive.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
- Estimated Construction Start: Fall 2025
- Estimated Construction End: Fall 2026