Bayhomes Drive Drainage Improvements

Project Number: 40-B30846

Project Scope:

The project has two phases. Phase 1A - Design and construction of right of way improvements including roadway reconstruction, milling and resurfacing, drainage, minor driveway and sidewalk work and installation of one new injection well, Phase 1B - Deep cleaning of the existing wells. Assessment of site. Design and construction of new drainage, including new injection wells, as applicable.

Project Estimate:

$1,050,000

Project Benefits and Impacts: 

The project will help alleviate localized flooding experienced by the community.

  • Number of properties impacted: Total = 35 Total (35 Residential)
  • Total property value protected: $60M

Project Boundaries:

The project limits are bounded by North Bay Homes Drive between SW 37 Avenue and South Bay Homes Drive.

Map indicating 40-B30846 project boundaries.png

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Estimated Construction Timeline:

  • Estimated Construction Start: Fall 2025
  • Estimated Construction End: Fall 2026