Replacement of 8 Seawalls in Edgewater - D2

This work was funded in part through a grant agreement from the Florida Department of Environmental Protection's Office of Resilience and Coastal Protection Resilient Florida Program. The views, statements, findings, conclusions, and recommendations expressed herein are those of the author(s) and do not necessarily reflect the views of the State of Florida or any of its subagencies.
February 2025.
Project Number: 40-B233810
Current Project Status (December 2025):
Design.
Project Scope:
Design and construction of eight seawalls in the Edgewater neighborhood. The works includes raising or replacing seawalls, dredging, bursting outfall pipes, installing manhole structures, tidal valves, manatee grates, riprap, guardrails, pavement milling and resurfacing, signage and pavement markings, street lighting, and landscaping.
Project Cost Estimate:
$3,541,662
Project Benefits and Impacts:
- Number of properties impacted: Total = 1090 (1067 Residential and 23 Non-Residential)
- Total property value protected: $1B
Project Boundaries:
The project limits are bounded by NE 22 Street along Biscayne Bay; NE 22 Terrace along Biscayne Bay; NE 25 Street along Biscayne Bay; NE 26 Street along Biscayne Bay; NE 27 Street along Biscayne Bay; NE 30 Street along Biscayne Bay; NE 30 Terrace along Biscayne Bay; NE 35 Street along Biscayne Bay.

Construction Schedule:
The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.
- Construction Start: February 2027
- Construction End: February 2028