Traffic Circle at North Bayshore Drive

Project Number: 40-B203614

Current Project Status (December 2025):

Pre-Construction.

Project Scope:

Design and construction of a traffic circle and associated roadway improvements including drainage, sidewalks, ADA ramps, roadway reconstruction, landscaping, and lighting.

Project Cost Estimate:

$2,105,849 

Project Boundaries:

The project limits are bounded by North Bayshore Drive from NE 15 Street to NE 17 Terrace.

Map illustrating the project boundaries of 40-B203614

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start: March 2026
  • Construction End: November 2026