SW 16 Terrace from SW 18 Avenue to SW 21 Avenue

Project Number: 40-B233819
Current Project Status (January 2026):
Construction.
Project Scope:
The new construction work consists of new asphalt, new drainage, new ADA ramps, and new valley gutter.
Project Cost Estimate:
$730,864
Project Boundaries:
The project limits are bound by SW 16 Terrace from SW 18 Avenue to SW 21 Avenue.

Road Closures:
Please note that some road closures may be necessary during the construction period; however, they will be carefully sequenced to minimize disruption to residents
Construction Schedule:
The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.
- Construction Start: January 2026
- Construction End: April 2026