Silver Bluff Traffic Flow Modification

Citizen's Independent Transportation Trust Logo

Project Number: 40-B243604

Current Project Status (July 2025):

Planning/ A/E Selection

Project Scope:

Traffic study for traffic calming, safety improvements and movement restrictions. Assessment of twenty-six locations for traffic calming device installations; balloting of applicable locations; design and construction of traffic calming devices at eligible locations.

Project Cost Estimate:

$7,776,837

Project Benefits and Impacts:

  • Number of properties impacted: Total = 295 (179 Residential and 116 Non-Residential)
  • Total property value protected: $216M

Project Boundaries:

The project limits are bounded by

Phase I

1. SW 16 Ave between SW 22 ST and SW 22 Ter (Choker, Median or Gateway)
2. SW 16 Ave between SW 22 Ter and SW 23 St (Speed Cushion or Hump)
3. 
SW 16 Ave and SW 23 St (Raised Intersection)
4. 
SW 16 Ave between SW 1 Ave and SW 23 Ter (Street Closure)
5. 
SW 1 Ave and SW 3 Ave (Realignment)
6. 
SW 3 Ave between SW 14 Ave and SW 16 Ave (High Visibility Crosswalk)
7. 
SW 23 St and SW 3 Ave (Roundabout/Traffic Circle)

Phase II

8. SW 14 Ave and SW 23 St (Raised Intersection)
9. 
SW 23 St between SW 14 Ave and SW 16 Ave (Speed Cushion or Hump)
10. 
SW 23 St between SW 16 Ct and SW 17 Ave (Choker, Median or Gateway)
11. 
SW 14 Ave and SW 3 Ave (Roundabout/Traffic Circle)

Phase III

12. SW 22 St and SW 13 Ave (Curb Extension)
13. 
SW 13 Avenue between SW 22 St and SW 22 Ter (Lane Restriping/Reconfiguration)
14. 
SW 22 Ter between SW 3 Ave and SW 13 Ave (Realignment)
15. 
SW 13 Ave between SW 22 Ter and SW 3 Ave (Realignment)
16. 
SW 13 Ave and SW 3 Ave (Roundabout/Traffic Circle)
17. 
SW 1 Ave between SW 16 Ave and SW 16 Ct (Raised Crosswalk)
18. 
SW 1 Ave between SW 16 Ct and SW 17 Ave (Raised Crosswalk)
19. SW 14 Ave between SW 22 St and SW 22 Ter (Choker, Median or Gateway)
20. 
SW 16 Ct between SW 22 St and SW 23 St (Choker, Median or Gateway)
21. 
SW 16 Ct between SW 22 St and SW 23 St (Speed Cushion or Hump)
22. 
SW 16 Ct between SW 23 St and SW 1 Ave (Speed Cushion or Hump)
23. 
SW 16 Ct between SW 23 St and SW 1 Ave (Choker, Median or Gateway)
24. 
SW 22 Ter between SW 13 Ave and SW 14 Ave (Speed Cushion or Hump)
25. 
SW 22 Ter between SW 14 Ave and SW 16 Ave (Speed Cushion or Hump)
26. 
SW 23 Ter between SW 14 Ave and SW 16 Ave (Speed Cushion or Hump)

Map illustrating the project boundaries of 40-B243604

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Estimated Construction Timeline:

Subject to change.

  • Estimated Construction Start (Phase I): January 2027
  • Estimated Construction End (Phase I): Summer 2027