Auburndale Traffic Device at SW 32 Avenue and SW 2 Street

Project Number: 40-B173655
Current Project Status (June 2025):
Design completed. The design is completed, and 100% plans were approved by RPW in April 2023.
Project Scope:
Design and construction of a raised intersection and associated and right-of-way improvements including roadway reconstruction, milling and resurfacing, ADA ramps, drainage system, pavement markings and signage.
Note: This project will be built under B-223802 Auburndale Neighborhood Flood Improvements.
Project Scope Estimate:
$1,335,790
Project Benefits and Impacts:
- Number of properties impacted: Total = 4 Residential
- Total property value protected: $1.6M
Project Boundaries:
The project limits are bounded by intersection of SW 32 Avenue and SW 2 Street.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
Subject to change.
- Estimated Construction Start: Summer 2025
- Estimated Construction End: Spring 2026
Provide your feedback about this project here