NW 8 Av from NW 41 St to the south end Drainage & Roadway Improvements

Project Number: 40-B30262

Current Project Status:

Construction.

Project Scope:

New asphalt, new drainage, new sidewalks, new ADA ramps, new valley gutter and new curb and gutter.

Project Cost Estimate:

$93,080

Project Boundaries:

The project limits are bounded by NW 8th avenue from NW 41st street to the south end.

Map illustrating the project boundaries of 40-B30262

Road Closures:

Some road closures may be necessary during construction; however, they will be carefully planned and sequenced to minimize inconvenience and ensure continued access for residents.

Estimated Construction Timeline:

(Subject to change based on project conditions)

  • Planned Start Date: February 2026
  • Planned Completion Date: April 2026

Disclaimer: The timeline provided is an estimate and may be adjusted due to factors such as weather conditions, or other unforeseen circumstances.