NW 8 Av from NW 41 St to the south end Drainage & Roadway Improvements
Project Number: 40-B30262
Current Project Status:
Construction.
Project Scope:
New asphalt, new drainage, new sidewalks, new ADA ramps, new valley gutter and new curb and gutter.
Project Cost Estimate:
$93,080
Project Boundaries:
The project limits are bounded by NW 8th avenue from NW 41st street to the south end.

Road Closures:
Some road closures may be necessary during construction; however, they will be carefully planned and sequenced to minimize inconvenience and ensure continued access for residents.
Estimated Construction Timeline:
(Subject to change based on project conditions)
- Planned Start Date: February 2026
- Planned Completion Date: April 2026
Disclaimer: The timeline provided is an estimate and may be adjusted due to factors such as weather conditions, or other unforeseen circumstances.