40-B30737 Fairview Flood Mitigation
Fairview Flood Mitigation
Project No.: 40-B 30737
Location: South Bayshore Lane/East Fairview Street and West Fairview Street
This project is Located in District 2
Notice of Construction Work
The City of Miami will be making much needed improvements and repairs during the next few months. Personnel and equipment from Terra Hyle Contractors, Inc. will be working in your neighborhood during this time.
Scope of Work
Drainage Improvements
Roadway Improvements
Furnish & install 8-inch D.I. water main
New concrete sidewalks
Repair of Driveway Approaches
Swale Restoration
Pavement markings
Signage
New ADA ramps
Construction Timeframe
Construction for this project is anticipated to commence in March 2019 and is anticipated to be completed by January 2020. Please note that this schedule may be subject to change due to adverse weather or other unexpected conditions.
Estimated Construction Cost
$ 698, 755
Contractor
Terra Hyle Contractors, Inc.
Construction Hours
Monday through Friday, 8am to 5pm
Maintenance of Traffic (MOT)
All efforts will be made to minimize the effects of construction activities to area residents, schools, businesses and motorists.