NW 13 Street from NW 35 Avenue to NW 37 Avenue

Citizens' Independent Transportation Trust Logo

Project Number: 40-B50104

Current Project Status (January 2026):

Construction.

Project Scope:

Design and construction of roadway and stormwater infrastructure improvements including roadway reconstruction, milling and resurfacing, ADA ramps, sidewalks, valley gutters, curbs and gutters, new and upsized stormwater inlets and pipes, exfiltration trenches, signage and pavement markings. This project also includes a Joint Participation Agreement (JPA) with Miami-Dade Water and Sewer (MDWASD) for the installation of an 8-inch water main, fire hydrants, and water services. Project limit being extended to include design and construction of swale restoration and drainage improvements along NW 35 Avenue from NW 13 Street to SR-836.

Project Cost Estimate:

$3,258,735

Project Boundaries:

The project limits are bounded by NW 13 Street from NW 35 Avenue to NW 37 Avenue. Project limit being extended to include design and construction of swale restoration and drainage improvements along NW 35 Avenue from NW 13 Street to SR-836 (yellow).

Map illustrating the project boundaries of 40-B50104

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start: May 2025
  • Construction End: June 2026