NW 13 Street from NW 35 Avenue to NW 37 Avenue

Project Number: 40-B50104
Current Project Status:
Construction.
Project Scope:
Design and construction of roadway and stormwater infrastructure improvements including roadway reconstruction, milling and resurfacing, ADA ramps, sidewalks, valley gutters, curbs and gutters, new and upsized stormwater inlets and pipes, exfiltration trenches, signage and pavement markings. This project also includes a Joint Participation Agreement (JPA) with Miami-Dade Water and Sewer (MDWASD) for the installation of an 8-inch water main, fire hydrants, and water services.
Project Cost Estimate:
$3,258,735
Project Benefits and Impacts:
- Number of properties impacted: Total = 38 Residential
- Total property value protected: $17M
Project Boundaries:
The project limits are bounded by NW 13 Street from NW 35 Avenue to NW 37 Avenue.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
Subject to change.
- Estimated Construction Start: Spring 2025
- Estimated Construction End: Spring 2026