NW 35 Av from NW 13 St to Dolphin Expwy Roadway & Drainage Improvement

Project Number: 40-B50104

Current Project Status:

Construction.

Project Scope:

The new construction work consists of new asphalt, new drainage, and new valley gutter.

Estimated Costs:

$150,000

Project Boundaries:

The project limits are bound by NW 35th Ave from NW 13th Street to Dolphin Expressway.

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Map illustrating the project boundaries of 40-B50104

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start Date: June 2026
  • Construction End Date: August 2026