Ohio St from Shipping Ave to Day Ave Drainage and Roadway Improvements

Project Number: 40-B30262

Current Project Status:

Construction.

Project Scope:

The project includes drainage improvements, road restoration and reconstruction, sidewalk improvements, pedestrian ramps, driveway approaches, pavement markings and signage. The proposed drainage will include new curb and/or gutter structures, and exfiltration trenches.

Project Cost Estimate:

$202,862

Project Boundaries:

The project limits are bound by Ohio St from Shipping Ave to Day Ave.

Map illustrating the project boundaries of 40-B30262

Road Closures:

Some road closures may be necessary during construction; however, they will be carefully planned and sequenced to minimize inconvenience and ensure continued access for residents.

Estimated Construction Timeline:

(Subject to change based on project conditions)

  • Estimated Construction Start: April 2026
  • Estimated Construction End: May 2026

Disclaimer: The timeline provided is an estimate and may be adjusted due to factors such as weather conditions, or other unforeseen circumstances.