South Grove Traffic Phase II

Citizens' Independent Transportation Trust Logo

Project Number: 40-B253604

Current Project Status (December 2025):

Construction.

Project Scope:

Assessment of ten locations for traffic calming device installations; balloting of applicable locations; design and construction of traffic calming devices at eligible locations.

Project Cost Estimate:

$555,991

Project Boundaries:

The project limits are bounded by

19. Avocado Ave between Douglas Rd and Plaza St (Speed Table)
20. Avocado Ave between Plaza St and Hibiscus St (Speed Table)
29. Crawford Ave between Frantz Rd and Justison Rd (Speed Table)
30. Palmetto Ave between Douglas Rd & Plaza St (Speed Table)
31. Palmetto Ave between Plaza St and Hibiscus St (Speed Table)
32. Royal Palm Ave between Douglas Rd and Plaza St (Speed Hump)
33. Royal Palm Ave between Plaza St and Hibiscus St (Speed Table)
34. Pomona Ave between Le Jeune Rd and La Playa Blvd (Speed Table)
35. Ventura Ave between Le Jeune Rd and La Playa Blvd (Speed Table)
36. El Prado Blvd between La Playa Blvd and Braganza Ave (Speed Table)

Map illustrating the project boundaries of 40-B253604

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start: November 2025
  • Construction End: March 2026