Tamiami Canal Blvd Improvement Project
Project Number: 40-B243600
Project Scope:
Design and construction of right-of-way improvements including roadway reconstruction, milling and resurfacing, drainage system, 8-inch water main, water services, fire hydrants, sidewalks, valley gutters, curbs and gutters, driveway approaches, on-street parking, ADA ramps, pavement markings and signage, landscaping, and lighting.
Project Cost Estimate:
$7,215,420
Project Benefits and Impacts:
- Number of properties impacted: Total = 61 (52 Residential and 9 Non-Residential)
- Total property value protected: $31M
Project Boundaries:
The project limits are bounded by Tamiami Boulevard between SW 71 Avenue and SW 72 Avenue. SW 71 Avenue between Flagler Street and SW 4 Street. SW 3 Street between SW 71 Avenue and SW 72 Avenue.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
- Estimated Construction Start: Fall 2024
- Estimated Construction End: Summer 2026
Provide your feedback about this project here