Tamiami Canal Blvd Improvement Project

Project Number: 40-B243600
Current Project Status (November 2025):
Phase 1: Construction Completed!
Phase 2: Design.
Project Scope:
Design and construction of right-of-way improvements including roadway reconstruction, milling and resurfacing, drainage system, 8-inch water main, water services, fire hydrants, sidewalks, valley gutters, curbs and gutters, driveway approaches, on-street parking, ADA ramps, pavement markings and signage, landscaping, and lighting.
Project Phases:
Phase I: Watermain extension and roadway improvements in front and in rear of Badia Center.
Phase II: Roadway and drainage improvements for the remaining project.
In-House: SW 72nd Avenue from SW 4th Street to Tamiami Blvd.
Project Cost Estimate:
$7,215,420
Project Boundaries:
The project limits are bounded by
- SW 71 Avenue between Flagler Street and SW 4 Street
- Tamiami Boulevard between SW 71 Avenue and SW 72 Avenue
- SW 3 Street between SW 71 Avenue and SW 72 Avenue

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Construction Schedule:
The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.
- Construction Start (Phase II): TBD
- Construction End (Phase II): TBD