Tamiami Canal Blvd Improvement Project

Project Number: 40-B243600

Project Scope:

Design and construction of right-of-way improvements including roadway reconstruction, milling and resurfacing, drainage system, 8-inch water main, water services, fire hydrants, sidewalks, valley gutters, curbs and gutters, driveway approaches, on-street parking, ADA ramps, pavement markings and signage, landscaping, and lighting.

Project Cost Estimate:

$7,215,420

Project Benefits and Impacts:

  • Number of properties impacted: Total = 61 (52 Residential and 9 Non-Residential)
  • Total property value protected: $31M

Project Boundaries:

The project limits are bounded by Tamiami Boulevard between SW 71 Avenue and SW 72 Avenue. SW 71 Avenue between Flagler Street and SW 4 Street. SW 3 Street between SW 71 Avenue and SW 72 Avenue.

Map indicating 40-B243600 Project Boundaries.png

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Estimated Construction Timeline:

  • Estimated Construction Start: Fall 2024
  • Estimated Construction End: Summer 2026

Provide your feedback about this project here