SW 30 Ave from SW 27 Ln to SW 27 Ter Roadway and Drainage Improvements

Project Number: 40-B30262

Current Project Status:

Construction.

Project Scope:

The new construction work consists of new asphalt, new drainage, and swale restoration.

Estimated Costs:

$154,828

Project Boundaries:

The project limits are bound by SW 30 Ave from SW 27 Ln to SW 27 Ter.

Map illustrating the project boundaries of 40-B30262

 

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start Date: July 2026
  • Construction End Date: September 2026