SW 72nd Avenue from SW 4th Street to Tamiami Blvd

Project Number: 40-B243600
Current Project Status (October 2025):
Ready for construction.
Project Scope:
The new construction work consists of new asphalt, new drainage, new ADA ramps, new curb and gutter and a manatee grate associated with an existing outfall.
Project Cost Estimate:
$419,286
Project Boundaries:
The project limits are bound by SW 72 Ave from SW 4 ST To Tamiami Blvd.

Road Closures:
During the construction period, certain road closures may be necessary. These closures will be carefully planned and sequenced to minimize inconvenience and ensure continued access for residents whenever possible.
Estimated Construction Timeline:
The following dates are estimates and may be adjusted due to weather conditions, or other unforeseen factors.
- Estimated Start Date: October 2025
- Estimated Completion Date: January 2026