Allapattah Neighborhood Flood Improvements


This work was funded in part through a grant agreement from the Florida Department of Environmental Protection's Office of Resilience and Coastal Protection Resilient Florida Program. The views, statements, findings, conclusions, and recommendations expressed herein are those of the author(s) and do not necessarily reflect the views of the State of Florida or any of its subagencies.
December 2023.
Project Number: 40-B233815
Current Project Status (January 2026):
Design.
Project Scope:
Design and construction of stormwater infrastructure and associated roadway improvements including new and upsized stormwater inlets and pipes, exfiltration trenches, gravity drainage wells, roadway reconstruction, milling and resurfacing, ADA ramps, signage and pavement markings. This project also includes a requested Joint Participation Agreement (JPA) with Miami-Dade Water and Sewer Department (MDWASD) for water main system betterments. The project scope was revised to exclude NW 29 St between NW 6 Ct and NW 14 Ave and NW 10 Ave between NW 28 St and NW 29 Ter due to limited funding. Drainage analysis was performed to ensure the removal of these streets would not impact the overall drainage flow.
Project Cost Estimate:
$62,674,641
Project Benefits and Impacts:
The project will help alleviate localized flooding experienced by the community.
- Number of properties impacted: Total = 938 Total (749 Residential and 189 Non-residential)
- Total property value protected: $800M
Project Boundaries:
The project limits are bounded by NW 31st Street to the North, NW 23rd Street to the South, NW 7th Avenue to the West, and NW 14th Avenue to the East.

Road Closures:
Some road closures will occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Construction Schedule:
The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.
- Construction Start: March 2027
- Construction End: April 2028