Miami River Greenway Curtis Park East

Citizens' Independent Transportation Trust Logo

Project Number: 40-B183603

Current Project Status (January 2026):

Construction Procurement.

Project Scope:

Design and construction of a greenway and associated right-of-way improvements including roadway reconstruction, milling and resurfacing, sidewalks, ADA ramps, drainage system, and lighting in accordance with the Miami River Greenway Master Plan. 

Project Cost Estimate:

$5,853,553

Project Boundaries:

The project limits are bounded by NW North River Drive between NW 22 Avenue and NW 24 Avenue.

Map illustrating the project boundaries of 40-B183603

Road Closures:

Some road closures will occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start: April 2026
  • Construction End: April 2027

MRG at Curtis Park 1

Click here to download the April 22nd, 2022 Community Meeting Presentation(PDF, 2MB)

Additional Traffic Signs Throughout the Project

MRG at Curtis Park Traffic Signs Map