Kinloch Roadway Neighborhood Improvements

This work was funded in part through a grant agreement from the Florida Department of Environmental Protection's Office of Resilience and Coastal Protection Resilient Florida Program. The views, statements, findings, conclusions, and recommendations expressed herein are those of the author(s) and do not necessarily reflect the views of the State of Florida or any of its subagencies.
December 2021.
Project Number: 40-B213606 (Phase I) / 40-B213606A (Phase II)
Project Scope:
Design and construction of right-of-way improvements including roadway reconstruction, drainage system, ADA ramps, sidewalks, curbs and gutters, signing and pavement markings, and landscaping. This project also includes a Joint Participation Agreement (JPA) with the Miami-Dade Water and Sewer Department (MDWASD) for the installation of an 8-inch watermain, water service connections, and fire hydrants.
Project Phases:
Phase I (40-B213606): NW 3 St and between NW 47 Ave and NW 48 Ave; NW 48 Ave between West Flagler St and NW 3 St.
Phase II (40-B213606A): NW 47 Ct between West Flagler St and NW 3 St; NW Flagler Ter between NW 47 Ave and NW 48 Ave; NW 1 St between NW 47 Ave and NW 48 Ave, NW 2 St between NW 47 Ave and NW 48 Ave, NW 2 Terrace between NW 47 Ave and NW 48 Ave.
Project Cost Estimate:
$3,443,884
Project Benefits and Impacts:
- Number of properties impacted: Total = 160 (150 Residential and10 Non-residential)
- Total property value protected: $77M
Project Boundaries:
Phase I: NW 3 St and between NW 47 Ave and NW 48 Ave; NW 48 Ave between West Flagler St and NW 3 St.
Phase II: NW 47 Ct between West Flagler St and NW 3 St; NW Flagler Ter between NW 47 Ave and NW 48 Ave; NW 1 St between NW 47 Ave and NW 48 Ave, NW 2 St between NW 47 Ave and NW 48 Ave, NW 2 Terrace between NW 47 Ave and NW 48 Ave.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
- Estimated Construction Start (Phase I): Fall 2026
- Estimated Construction End (Phase I): Fall 2027
- Estimated Construction Start (Phase II): Winter 2026
- Estimated Construction End (Phase II): Winter 2028
Provide your feedback about this project here