Clemente Park Neighborhood Flood Improvements

Miami Forever Bond LogoFlorida Department of Environmental Protection Logo

This work was funded in part through a grant agreement from the Florida Department of Environmental Protection's Office of Resilience and Coastal Protection Resilient Florida Program. The views, statements, findings, conclusions, and recommendations expressed herein are those of the author(s) and do not necessarily reflect the views of the State of Florida or any of its subagencies.
December 2023.

Project Number: 40-B233817

Current Project Status (April 2026):

  • The project is being delivered under a Design–Bid-Build model.
  • Design Notice to Proceed was issued in November 2024.
  • The project is currently in the design phase.
  • 60% design plans were completed in December 2025.
  • 90% plans (Permit Set) were submitted in March 2026, and permit applications are now underway.
  • Water main Design Notice to Proceed was issued in July 2025.
  • MDWASD Water Main design: 60% plans received approval in February 2026.
  • MDWASD Water Main design plans are anticipated to be completed in June 2026.
  • 100% full design anticipated to be completed in November 2026.
  • Invitation to Bid (anticipated) in November 2026
  • Construction Start (anticipated): July 2027
  • Construction Completion (anticipated): July 2028
  • Final Completion (anticipated) December 2028.

Project Scope:

Design and construction of stormwater infrastructure and right-of-way improvements including new and upsized stormwater inlets and pipes, gravity well, exfiltration trenches, roadway reconstruction, milling and resurfacing, curbs and gutters, ADA ramps, and signage and pavement markings. This project may also include a Joint Participation Agreement (JPA) with the Miami-Dade Water and Sewer Department (MDWASD) for the installation of an 8-inch water main, water services, and fire hydrants.

Project Cost Estimate:

$23,123,505

Project Benefits and Impacts:

The project will help alleviate localized flooding experienced by the community.

  • Number of properties impacted: Total = 393 (113 Residential and 280 Non-Residential)
  • Total property value protected: $435M

Project Boundaries:

The project limits are bounded by

  • NW 30 St between N Miami Ave and NW 3 Ave
  • NW 31 St between N Miami Ave and NW 3 Ave
  • NW 32 St between N Miami Ave and NW 3 Ave
  • NW 33 St between N Miami Ave and NW 3 Ave
  • NW 34 St between N Miami Ave and NW 3 Ave
  • NW 34 Ter between N Miami Ave and NW 1 Ave
  • NW 34 Ter between NW 2 Ave and NW 3 Ave
  • NW 35 St between N Miami Ave and NW 3 Ave
  • NW 37 St between NW 1 Ave and NW 3 Ave
  • NW 1 Ave between NW 30 St and NW 36 St

Map illustrating the project boundaries of 40-B233817

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Construction Schedule:

The timeline provided is an estimate and may change due to weather conditions or other unforeseen circumstances.

  • Construction Start: July 2027
  • Construction End: July 2028